Project Profiles
Biocell Construction and Flare Knock Out Remediation Sour Gas Facility
Alta Tech was retained by a major sour gas processing company to construct a biocell and remediate over 10,000m3 of contaminated soil at a flare knockout within a sour gas facility. Two delineation programs had been conducted at the flare knockout prior to remediation, which identified over 27,000m3 of hydrocarbon-impacted soil. Impacted soil was remediated with land farming treatment within the biocell.